|
Descriptions
DTS54 tri-phase 4-wire AC active electronic energy meter is adopting advance ASIC energy measure design, it is applicable for measurement of energy in AC electricity network. The meter is conform to GB/T17215-2002<< grade 1.0 and 2.0 static AC active energy meter>>
Features
1. The meter has the characteristic of small volume, light weight, high precision, low power consumption etc.
2. The meter has the function of bi-direction measurement.
3. The meter is adopting photoelectric coupler output test signal, LBD indicated the power consumption. The pulse of photoelectric is output proportionally with power consumption, for the different current point during the checkout, it can be chose form 1 to 16.
Main specification and technical parameter
4.Specification:
|
Specification and model |
Accuracy |
Rated voltage(V) |
Rated current(A) |
|
DTS54 |
1.0 |
3X57.5/100 |
1.5(6);3(6)
5(20);10(40)
20(80);30(120) |
|
3X220/380 |
2. Basic error: ( tri-phase balance load)
|
Load current |
Power factor |
Basic error(%) |
|
0.05Ib |
1.0 |
±1.5 |
|
0.1Ib~Imax |
1.0 |
±1.0 |
|
0.1Ib |
0.5 (Lagging ) |
±1.5 |
|
0.8 (Leading) |
±1.5 |
|
0.2Ib~Imax |
0.5 (Lagging) |
±1.0 |
|
0.8 (Leading) |
±1.0 |
3.Parameter:
Power consumptions: voltage circuit <10VA or 2W, current circuit <10VA
Start current: 0.4%Ib(grade 1.0), 0.5%Ib(grade 2.0)
Latent start: the meter has logic anti latent start circuit
4. Dimension: length x width x height =185mm x 275mm x 75mm
5. Connection diagram:
三相四线1.5(6)A经电流互感器接入式电度表接线图 三相四线直接接入式电度表接线图
Tri-phase 4-wire 1.5(6)A through current transformer connect energy meter diagram
Tri-phase 4-wire direct connect energy meter diagram.
Transportation and storage
1. The meter should be avoid to strike violently during transport and open, and transported and stored according to GB/T15464-1995 <<apparatus and meter packing technical requirements>>.
2. Keep the meter in original package, the temperature should be -25℃~+70℃,relative humidity is not more than 85%, no acoustic substance is in the air
3. When place the meter on the shelf, the height should be not more than five cartons, after open, the meter should not be placed more than 10 pieces in height.
Service life time:
The average service life time is more than ten years.
|